- Client: Can Pack India
- Project Scope: SITC of 2 x 2000 KVA Diesel Rotary UPS Systems
Challenges:
- Tight project timeline for plant inauguration.
- Need for highly stable power for high-speed production lines.
Execution Strategy:
- Fast-tracked engineering, procurement, and commissioning.
- Detailed load profiling to configure DRUPS settings for can-manufacturing machines.
- Coordinated installation with site construction team to avoid overlaps.
Unique Highlights:
- Project completed in 8 months – from concept to commissioning.
- DRUPS system ensures less than 1 second switchover.
- Plant inaugurated by the Honorable Industrial Minister of Haryana.
Client Impact:
- Achieved reliable power with zero production downtime.
- Boosted confidence for future plant expansions.
- Enabled smooth launch of production in a new region.